DATA CENTRES

Planning and Scheduling for Data Centres

A data centre is late when the power and cooling path is late, even if the building looks finished. The schedule has to follow that path.

Data centres

Plan the power path, not just the building

Data-centre programmes promise a megawatt date. That date depends on transformers, switchgear, generators, cooling plant, controls and a commissioning sequence that cannot be crashed by adding labour at the end.

We schedule design freeze, procurement slots, deliveries, installation by hall or data room, and the test stages that lead to energisation. Level 1 to integrated systems testing is logic, not a single bar called commissioning.

Phased delivery is normal. Later halls should not inherit float that the first energisation has already consumed. Coding by hall, system and contractor keeps that visible.

On the programme

What has to be got right

Long-lead plant

Switchgear and cooling equipment often set the date. Factory slots and delivery need activities of their own.

Commissioning stages

Component, system and integrated tests have predecessors. Skipping the logic is how teams discover a late hall in the last month.

Hall phasing

Each hall or data suite needs a path to energisation that can be reported on its own.

How we help

How EVM Solutions supports the team

Planning, scheduling and project controls from a Manchester-based consultancy, deployed to the programme rather than tied to a local office in every city.

Energisation schedules

A baseline aimed at the power-on date, with building works in their real place on the path.

Vendor integration

Manufacturer dates linked to installation so a slipped factory slot is seen early.

Client dashboards

Hall-by-hall progress for owners who are tracking more than one site.

FAQ

Questions we are often asked

Do you plan both the shell and the fit-out of the technical space?

Yes. Shell, MEP and commissioning sit in one schedule so the energisation date has a traceable path.

Can this align with an owner design standard?

Yes. We map the WBS to the owner stages and the contractor packages.

Where are these projects usually located?

We support data-centre programmes in the UK, the USA, the UAE and other regions. The location pages describe the local market. This page describes the sector.